Singapore Changi Airport T4 - Development of Terminal 4 Singapore Changi Airport (External and Bridge Works)
Client: |
Changi Airport Group |
Status: |
Completed |
Project type: |
Engineering |
Completion: |
2014 |
The Sub-Contract Works for the External Works and Bridge Works comprises of the following:
- Site Clearance & Demolition
- All Drainage System and Vehicle Pavement of the Proposed T4 & Slip Road Linking from PIE Into Airport Boulevard
- RC Works for Concrete Plinth for Floodlight, OG & Aircraft Plinth at Fixed Gangway @ Airside
- Retaining Wall for Proposed Slip Road from PIE into Airport Boulevard
- Vehicular Slab Over Bridge 1 & 2
- 600m length Vehicular Airside Bridge - AS-1 Bridge
- Vehicular Bridge LS-1 Bridge
- Access Ramp Bridge T4-1, T4-2 & T4-3 Bridges
- 240m length POB Bridge Linking SATS Kitchen to Airport Police Station